The Auditor General has published an audit report on the Kumundhoo Harbor Project that was contracted to Maldivian Democratic Party (MDP) Chairperson ‘Reeko’ Moosa Manik’s Heavy Load company by the Housing Ministry.
The Auditor General in his report noted that the work was assigned to Heavy Load in violation of article 8.25 of the State Finance Regulation.
‘’Article 8.25 of the Finance Regulation states that any work that costs more than Rf1.5 million (US$100,000) should be assigned to a party by the Tender Evaluation Board in an open bid, and that the interested parties should submit details of the work,’’ Auditor General said in the report. ‘’But the Kumundhoo Harbor Project was not assigned to the party accordingly.’’
According to the report, the project that was supposed to be finished in six months was finished in 31 months, and the government had to pay Rf 22.2 Million for a project originally budgeted at Rf 10.3 million project.

Become a member

Get full access to our archive and personalise your experience.


Already a member?

Discussion

No comments yet. Be the first to share your thoughts!

No comments yet. Be the first to join the conversation!

Join the Conversation

Sign in to share your thoughts under an alias and take part in the discussion. Independent journalism thrives on open, respectful debate — your voice matters.

Support independent journalism